Site icon Exam4Training

In what plan should these new rules be documented?

A project manager notices that the project is behind schedule because materials delivery was delayed. The procurement team informs the project manager that new government-imposed rules for the procurement of these materials caused this delay.

In what plan should these new rules be documented?
A . Project management
B . Communications management
C . Stakeholder engagement
D . Procurement management

Answer: D