In what phase is the nsk management plan created?

An initiative involves the development of new technology and leverages existing technologies It is determined critical by the program governance board and the program sponsor that a comprehensive risk management plan be put in place.

In what phase is the nsk management plan created?
A . Program definition
B. Program execution management
C. Program delivery
D. Program risk management planning

Answer: A