In what area should the project manager implement corrective actions?

A project status report shows that the earned value (EV) is 24.5. the schedule performance index (SPI) is 0.92, and the cost performance index (CPI) is 1.08.

In what area should the project manager implement corrective actions?
A . Project schedule
B . Stakeholder engagement
C . Resource management
D . Project cost

Answer: A