In the task scheduling process of YARN, which of the following tasks is the responsibility of the Application Master?

In the task scheduling process of YARN, which of the following tasks is the responsibility of the Application Master?
A . Applying for and receiving resources
B. Set up the running environment for the task
C. Allocate Containers
D. Start the Map or Reduce task

Answer: A