In the supplier enablement process, when does the buyer develop their compliance policy? Please choose the correct answer.

In the supplier enablement process, when does the buyer develop their compliance policy? Please choose the correct answer.
A . After the first wave is enabled
B . Before flight planning is initiated
C . Before the Project Notification letter is sent
D . After supplier training is conducted

Answer: C