In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.

In the Schedule Production app, which settings can you make in the planning strategy? Note: There are 3 correct answers to this question.
A . Fixed pegging (on/off)
B . Planning mode (bucket/sequence)
C . Finiteness level (0…1)
D . Direction (forward/backward)
E . Scheduling control (finite/infinite)

Answer: B,D,E