In the product Cost by Order component, what does the system calculate depending on the order status? 1 answer
In the product Cost by Order component, what does the system calculate depending on the order status? 1 answer
A . WIP at target costs or variances
B . WIP at actual costs or variances
C . WIP at planned costs or variances
D . Both WIP and variances or only variances
Answer: B