Exam4Training

In the preliminary analysis of the cutover project, which of the following aspects should be considered? (Multiple Choice)

In the preliminary analysis of the cutover project, which of the following aspects should be considered? (Multiple Choice)
A . Necessity
B . Feasibility
C . Risk
D . Cost

Answer: ABC