In the Plan Stakeholder Management process, expert judgment is used to:

In the Plan Stakeholder Management process, expert judgment is used to:
A . Provide information needed to plan appropriate ways to engage project stakeholders.
B . Ensure comprehensive identification and listing of new stakeholders.
C . Analyze the information needed to develop the project scope statement.
D . Decide the level of engagement of the stakeholders at each required stage.

Answer: D