In the period in question, the budget for staff overtime and bonuses is zero.
The actual expenditure is 2,900.
Is this variance:
A . Averse?
B . Favourable?
C . Adverse?
D . Zero?
Answer: C
Explanation:
The variance is adverse – more was spent than budgeted – this is not favourable.