In the middle of the Sprint, the customer decides that there are two new features she wants. The Product Owner could: (choose the best two answers)
A . Introduce these features at the next Daily Scrum.
B . Add these features to the Product Backlog.
C . Have the Scrum Master add these features to the current Sprint.
D . Ask the Developers to consider whether they can add these features to the current Sprint without endangering the Sprint Goal.
Answer: B, D
Latest PSPO-I Dumps Valid Version with 481 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund