In the information security system construction management cycle, which of the following actions is required to be implemented in the “check” link?

In the information security system construction management cycle, which of the following actions is required to be implemented in the “check” link?
A .  Safety management system design
B .  Implementation of the safety management system
C .  Risk assessment
D .  Safety management system operation monitoring

Answer: C