In Team Estimation…
A . Members of a group define what criteria will be used for determining the "Definition of Done”.
B. You estimate what roles will be necessary in order to complete user stories.
C. You first estimate the relative sizes of all stories, then assign numbers to them.
D. Each team is ranked in order of importance for completing a task.
Answer: C
Explanation:
An important decision to make when estimating or sizing work items is the unit in which you are doing so. (Choose Your WoW, Choose Estimation Unit, page 174).
Latest DASM Dumps Valid Version with 300 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund