In each Sprint Backlog at least one high priority process improvement items is existing.

In each Sprint Backlog at least one high priority process improvement items is existing.
A . False
B. True

Answer: A

Explanation:

Following the latest Scrum Guide, it is only optional to add process improvements to the Sprint Backlog!