Exam4Training

In developing a network the first task after listing the activities is to…

In developing a network the first task after listing the activities is to…
A . Define activity durations
B . Determine float
C . Determine the interdependencies of activities
D . Harmonise the activity to a calendar

Answer: C

Latest APM-PFQ Dumps Valid Version with 354 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version