In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?
In an Agile approach, at which meeting does a team examine the effectiveness of risk responses by conducting a risk audit?
A . Release planning
B . Sprint planning
C . Sprint Retrospective
D . Daily Scrum
Answer: C
Latest PMI-ACP Dumps Valid Version with 717 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments