In addition to Program Increment (PI) Objectives and uncommitted objectives, what also must be identified during PI Planning?

In addition to Program Increment (PI) Objectives and uncommitted objectives, what also must be identified during PI Planning?
A . Communication barriers and silos
B . Program risks
C . PI velocity goals
D . The chain of command

Answer: B