In addition to creating an internal and external profile of the organization, which of the following items is needed to define the scope of the supply chain transformation project?
A . Business description
B . Strategic background
C . Value proposition statement
D . SWOT analysis
Answer: B
Explanation:
According to the CTSC exam content manual1, the strategic background is one of the items needed to define the scope of the supply chain transformation project, along with the internal and external profile of the organization. The strategic background includes the vision, mission, values, goals, and objectives of the organization, as well as the drivers and enablers of the transformation.