Exam4Training

In a rolling forecast table, what can be used to determine the date to cut over to plan data?

In a rolling forecast table, what can be used to determine the date to cut over to plan data?
A . Look back x number of months
B. Last actual value
C. Look ahead x number of months
D. Current date with an offset

Answer: D

Exit mobile version