In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
A . The project is under budget and ahead of schedule.
B . The project is over budget and ahead of schedule.
C . The project is under budget and behind schedule.
D . The project is over budget and behind schedule.
Answer: B
Latest PK0-004 Dumps Valid Version with 574 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments