In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?

In a project with a of $235,000, the CPI is 0.80, and the SPI is 1.20. Based on this information, which of the following can the key stakeholders determine about the project?
A . The project is under budget and ahead of schedule.
B . The project is over budget and ahead of schedule.
C . The project is under budget and behind schedule.
D . The project is over budget and behind schedule.

Answer: B