In a project, what is the correct term for a group of dependencies, activities, and relationships sequenced in chronological order?
In a project, what is the correct term for a group of dependencies, activities, and relationships sequenced in chronological order?
A . Work breakdown structure
B . Project planning
C . Routing
D . Network
Answer: D