In a project that is feature-rich but time-poor, which is the most reasonable approach to risk analysis?
In a project that is feature-rich but time-poor, which is the most reasonable approach to risk analysis?
A . Conduct a full risk analysis, including weighted likelihood and impact ratings for each item
B . Use a lightweight approach and assign relative importance of each identified item
C . Skip the risk analysis step and proceed to test execution based on experience
D . Concentrate on the functional capabilities and disregard the physical capabilities of the device since those should be tested by the manufacturer
Answer: B
Explanation:
B is correct since this is a time challenged project. If there were adequate time, A might be the right answer, depending on the criticality of the product.
C is never a good idea since even minimal risk analysis is needed to focus the testing.
D is risky because the interaction of the application with the physical capabilities of the device still need to be tested.