In a make-to-stock (MTS) environment, the master production schedule (MPS) Is usually a schedule of which of the following types of items?
A . Phantom items
B . Finished goods items
C . Component/subassembly items
D . Raw material items
Answer: B
Explanation:
In a make-to-stock (MTS) environment, the master production schedule (MPS) is usually a schedule of finished goods items that are ready to be sold to customers. Phantom items, component/subassembly items, and raw material items are not typically scheduled in the MPS, but rather in the material requirements planning (MRP) system, which is driven by the MPS.
References:
CPIM 8.0 Exam Content Manual Preview, page 10, section 4.1.1
CPIM Part 1 Study Guide, page 66, section 4.1.1
CPIM Part 1 Learning System, Module 4, Lesson 1, Topic 1: Master Production Schedule