In a lean environment, the batch-size decision for planning "A" items would be done by:

In a lean environment, the batch-size decision for planning "A" items would be done by:
A . least total cost.
B . min-max system.
C . lot-for-lot (L4L).
D . periodic order quantity.

Answer: C

Explanation:

In a lean environment, the batch-size decision for planning “A” items would be done by lot-for-lot (L4L). L4L is an inventory management technique that orders exactly the quantity needed to meet the demand for each period. This minimizes the work in process, cycle time, and inventory holding costs. L4L is consistent with the lean principles of reducing batch sizes, eliminating waste, and responding to customer pull. The other options are not suitable for a lean environment, as they either order more than the demand (least total cost, min-max system, periodic order quantity) or incur more setup costs (least total cost, periodic order quantity).

References:

• [CPIM Part 2 – Section A – Topic 3 – Lean and Just-in-Time]

• Optimize Production Batch Sizes

• How to determine your Lot Size – Part 1