Exam4Training

Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.

Improvements that are outcome of the sprint retrospective can be added to the sprint backlog for the next sprint.
A . True
B. False

Answer: A

Explanation:

The scrum guide says: "The most impactful improvements are addressed as soon as possible. They may even be added to the Sprint Backlog for the next Sprint."

Latest PSD Dumps Valid Version with 120 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version