You are currently working on creating the activity list for an initiative in your organization.
What characteristic must be assigned to each task in your task list?
- A . Procurement needs
- B . Risk level
- C . Unique number
- D . Roles and responsibilities
Shelly is the business analyst for her organization and she’s working with Thomas to review the business requirements. They are discussing the identified requirements, how the requirements will transition to the operations, and the longevity of the solution. Thomas is concerned that the identified requirements may not map to the desired future state of the organization.
What business analysis task is Shelly facilitating in this scenario?
- A . Acceptance evaluation criteria definition
- B . Requirements quality assurance
- C . Validate requirements
- D . Stakeholder management
Which of the following are documented approaches to the business analysis work? Each correct answer represents a complete solution.
- A . Deming’s Quality Circle
- B . Lean
- C . Six Sigma
- D . Waterfall approach
You are the business analyst for your organization and working with the stakeholders to prioritize the requirements. The stakeholders are concerned about the financial impact of the requirements should some of them fail during the implementation. You would like to rank the risk tolerance of the stakeholders based on their comments about the solution and the requirements.
The following are the three categories of risk tolerance associated with the stakeholders except for which one?
- A . Neutrality
- B . Mitigation
- C . Risk-seeking
- D . Risk-aversion
Tracy is a business analyst for her organization and she’s gathered and identified the needed requirements for the solution scope.
What must Tracy do before she can begin managing the requirements? Choose the best answer.
- A . Tracy must decompose the requirements in WBS.
- B . Tracy must create cost-benefits analysis of each requirement to manage the benefits first.
- C . Tracy must identify roles, responsibilities, and owners of the requirements to fully manage the requirements.
- D . Tracy must communicate the requirements to the stakeholders for their consent and approval.
Ben is the business analyst for his organization. Ben is currently working on a solution to improve a laser printer. He has taken the laser printer apart, identified each component, and documented each component’s purpose.
What type of requirements organization is Ben doing in this scenario?
- A . Functional decomposition
- B . Process modeling
- C . Scope modeling
- D . Data modeling
You are the business analyst for your organization and you’re working with Fran on business analysis processes. Fran is a stakeholder who wants to ensure that your business analysis approach and activities are compatible with the project activities.
Of the following, what type of business analysis stakeholder is Fran?
- A . Regulator
- B . Project manager
- C . Sponsor
- D . Domain subject matter expert
You are a business analyst for your organization and you’re working with Mary. Mary wants to know what you need to complete the process of planning the business analysis approach if you’re already the business analyst for your organization.
Which of the following statements is true regarding the plan business analysis approach?
- A . The plan business analysis approach describes the amount of budget needed for the requirements elicitation.
- B . The plan business analysis approach is required to select an approach that will perform business analysis.
- C . The plan business analysis approach describes the processes the business analyst will or will not do, based on the time and budget available.
- D . The plan business analysis approach describes the amount of time needed for the business analysis approach.
You are the business analyst for a large software development project. There are several issues that must be resolved by certain dates or the problem will prevent the project from advancing.
What technique can you use to track problems with the requirements?
- A . Issue tracking
- B . RTM
- C . Problem tracking
- D . Baselining
Which one of the following statements is most true about changing requirements in a change-driven approach to business analysis and requirements management?
- A . Change-driven approaches must use a change control system with a change control board.
- B . Change-driven approaches only use a change control system for approved changes.
- C . Change-driven approaches don’t use a formal change control process.
- D . Change-driven approaches are driven by change control processes.