If you change the status of a Kanban container in an event-driven control cycle from "Fu happens with the Kanban container?
If you change the status of a Kanban container in an event-driven control cycle from "Fu happens with the Kanban container?
A . It is set to status "Empty" (red color) and replenishment is triggered
B . It stays in status full until the goods issue for the components has been posted
C . It is set to status "Empty" (red color), however, NO replenishment is triggered
D . It is deleted
Answer: D
Latest C_S4CMA_2308 Dumps Valid Version with 159 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments