If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A . Checkpoint Report
B . Highlight Report
C . Issue Report
D . Product Status Account
Answer: C
Explanation:
When the Project Board instructs the Project Manager to implement a request for change, details of that change are contained in an Issue Report. This document provides a detailed description of the issue, its evaluation, and the decisions regarding its resolution, including any changes to be implemented.
Reference: PRINCE2® Foundation official study guide and online resources.
These answers are based on the latest materials and guidelines from the PRINCE2® Foundation documentation and should reflect the most current practices and theoretical underpinnings of the methodology.
Latest PRINCE2 7 Foundation Dumps Valid Version with 463 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund