If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?

If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A . Checkpoint Report
B . Highlight Report
C . Issue Report
D . Product Status Account

Answer: C

Explanation:

When the Project Board instructs the Project Manager to implement a request for change, details of that change are contained in an Issue Report. This document provides a detailed description of the issue, its evaluation, and the decisions regarding its resolution, including any changes to be implemented.

Reference: PRINCE2® Foundation official study guide and online resources.

These answers are based on the latest materials and guidelines from the PRINCE2® Foundation documentation and should reflect the most current practices and theoretical underpinnings of the methodology.

Subscribe
Notify of
guest
0 Comments
Inline Feedbacks
View all comments