If the Product Owner has concerns about the Definition of Done (DoD) – what should the Product Owner do?

If the Product Owner has concerns about the Definition of Done (DoD) – what should the Product Owner do?
A . The Product Owner should discuss the Definition of Done with the Development Team.
B. The Product Owner should change the Definition of Done.
C. The Product Owner should ask the Scrum Master to change the Definition of Done.

Answer: A

Explanation:

The Definition of Done is owned by the Development Team. Therefore, the Definition of Done has to be changed by the Development Team. The Definition of Done should’t be changed in the middle of the Sprint.