If the owner responds today confirming the virtual machine is no longer needed, how many days will elapse before the virtual machine is destroyed?
A vRealize Automation Tenant Administrator has identified a virtual machine with low resource utilization. The owner has been given 5 days to respond to the reclamation request. The blueprint used to build the virtual machine has an archive period of 10 days and there are 21 days left in the original machine lease.
If the owner responds today confirming the virtual machine is no longer needed, how many days will elapse before the virtual machine is destroyed?
A . 10 days
B . 31 days
C . 21 days
D . Today
Answer: A
Latest 2V0-731 Dumps Valid Version with 123 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments