If the advanced planning capability is selected when the audit plan is created, what extra related lists display on the engagement record in addition to the related lists displayed with basic planning?

The advanced planning capability enables integration of Advanced Audit with PPM.

If the advanced planning capability is selected when the audit plan is created, what extra related lists display on the engagement record in addition to the related lists displayed with basic planning? (Choose three.)
A . Time card
B. Resource plan
C. Entities
D. Cost plan
E. Milestones

Answer: A,D,E