If the Active Security Management Server fails or if it becomes necessary to change the Active to Standby, the following steps must be taken to prevent data loss. Providing the Active Security Management Server is responsible, which of these steps should NOT be performed:

If the Active Security Management Server fails or if it becomes necessary to change the Active to Standby, the following steps must be taken to prevent data loss. Providing the Active Security Management Server is responsible, which of these steps should NOT be performed:
A . Rename the hostname of the Standby member to match exactly the hostname of the Active member.
B . Change the Standby Security Management Server to Active.
C . Change the Active Security Management Server to Standby.
D . Manually synchronize the Active and Standby Security Management Servers.

Answer: A