If someone wanted to constrain a project’s end date so that any project slippage would cause negative float, they would do so by using
If someone wanted to constrain a project’s end date so that any project slippage would cause negative float, they would do so by using
A . Finish-no-earlier constraint on the first activity
B . Finish-no-earlier constraint on the last activity
C . Finish-no-later constraint on the last activity
D . Start-no-later constraint on the first activity
Answer: C