If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)

If Scenario Planning for PPM is installed, a portfolio manager can access the Portfolio Planning Workbench by navigating to which of the following? (Choose two.)
A . Project module
B . Program Workbench
C . Portfolio Planning related link
D . Portfolio Planning Workbench module

Answer: CD