If no action is taken, how many calendar days can pass before the SLA fails?

You create a service level agreement {SLA) that wilt fail after seven days. You select a service calendar that uses 24-hour work days and no holidays. Saturday and Sunday are configured to be non-working days.

If no action is taken, how many calendar days can pass before the SLA fails?
A . 5 days
B . 7 days
C . 9 days
D . 11 days

Answer: A