Exam4Training

If an activity time within a critical path is increased, which of the following is most likely to occur?

If an activity time within a critical path is increased, which of the following is most likely to occur?
A . The project will be delayed.
B . Additional resources will have to made available.
C . Costs will increase.
D . All activities in the project will be affected.

Answer: A

Latest CMQ-OE Dumps Valid Version with 348 Q&As

Latest And Valid Q&A | Instant Download | Once Fail, Full Refund

Exit mobile version