Exam4Training

If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
A . Only 1 is true
B . Only 2 is true
C . Both 1 and 2 are true
D . Neither 1 or 2 are true

Answer: C

Explanation:

Both statements are true within the PRINCE2® framework. Statement 1 is accurate as the Project Manager does have day-to-day control within the limits set by the Project Board for a management stage. Statement 2 is also correct because if a Team Manager forecasts a deviation beyond Work Package tolerances, it should indeed be referred to the Project Manager.

Reference: PRINCE2® Foundation official study materials.

Exit mobile version