If a process improvement team has been asked to focus on this problem, which of the following steps should the team take first?

A U.S. manufacturer has an offshore, single-source supplier for a critical part. Many of the parts are rejected by receiving inspection because they are out of tolerance, but the material review board subsequently accepts those rejects.

If a process improvement team has been asked to focus on this problem, which of the following steps should the team take first?
A . Review the specification limits with engineering;
B . Perform 100% inspection an incoming parts from this supplier
C . Require the supplier to provide a certificate of conformance tor each lot
D . Reject all lots until the supplier corrects the problem

Answer: A