If 5 of the machines, working simultaneously at this rate, produce a total of 200 such parts in 4 days, how many days will it take all 6 machines, working simultaneously at this rate, to produce a total of 300 such parts?
At a factory. 6 machines work independently at the same constant rate to produce certain parts.
If 5 of the machines, working simultaneously at this rate, produce a total of 200 such parts in 4 days, how many days will it take all 6 machines, working simultaneously at this rate, to produce a total of 300 such parts?
A . 4.0
B . 4.5
C . 5.0
D . 5.5
E . 6.0
Answer: C
Latest GRE Dumps Valid Version with 407 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund
Subscribe
Login
0 Comments
Inline Feedbacks
View all comments