Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.
A . Stage Plan
B . Communication Management Strategy
C . Follow-on action recommendations
D . Quality Management Strategy
Answer: B
Explanation:
The Communication Management Strategy should be referred to at the end of a stage to check whether there is a requirement to send copies of the End Stage Report to external interested parties. This document outlines how, when, and by whom information will be disseminated throughout the project, including communication with external stakeholders.
Reference: PRINCE2® Foundation official study guide and materials.