Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.
A . project cost tolerance
B . stage cost tolerance
C . Work Package cost tolerance
D . product cost tolerance
Answer: C
Explanation:
A Project Manager agrees on the Work Package cost tolerances with a Team Manager. This agreement defines the acceptable cost variance within which the Team Manager can operate without needing further approval.
Reference: PRINCE2® Foundation official study materials.