Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.

Identify the missing word in the following sentence. A member of the Project Board is responsible for [ ? ] assurance.
A . quality
B . supplier
C . risk
D . product

Answer: A

Explanation:

A member of the Project Board is responsible for quality assurance in PRINCE2. Quality assurance is concerned with ensuring that the project’s products meet the quality requirements set out in the project and that the project adheres to the appropriate corporate, programme management, or customer quality standards.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources