Which statement is true about routes?
- A . A route can only be applied to a work order by a PM.
- B . A route’s sequence numbers are fixed after it is activated.
- C . A route can create work orders for locations or assets, not both.
- D . Route Stops that become work order tasks cannot have job plans.
To minimize Start Center load times, end users can see detailed KPI information from which application?
- A . Analytics
- B . KPI Viewer
- C . KPI Manager
- D . KPI Templates
A buyer runs a BIRT report which details Supplier Compliance. The buyer needs to further analyze the data in a spreadsheet to include an additional graph before reviewing the information with the manager.
Which process transforms the data?
- A . Export
- B . Preview
- C . Application Export
- D . Report Transformation
A workflow process has been revised and the new revision made active.
What happens to records that had already been routed into that workflow process before this was done?
- A . They continue running in the earlier revision.
- B . They are removed from workflow and must be restarted manually.
- C . They switch to running in the new revision as that is the only active revision.
- D . They are removed from workflow and are started in the new revision by a cron task.
A company has critical and time sensitive processes and tasks foe repairing assets. The company maintenance supervisor would like to be notified if any of the time sensitive tasks are overdue.
What application would the company use to configure this?
- A . Workflow
- B . Escalation
- C . Cron Task
- D . Interaction
The business analyst for the purchasing department of a company is creating a workflow process for purchase requisitions. A requirement is to branch the process to different approval groups based on a cost evaluation.
Which method is used to implement this in Workflow Designer?
- A . A condition node with an expression.
- B . A manual input with a custom action list.
- C . An interaction node to review the PR lines.
- D . A call out to the purchasing thresholds of the roles.
A company wants to refuse receipt on 2 of 7 items from a single PO Line which does not require inspection.
Which procedure will accomplish this and maintain the correct inventory balance?
- A . Save the Receipt, Click the Select Receipts to Void button, Change the quantity to 5.
- B . Save the Receipt, Click the Select Items for Return button on the PO Line, Change the quantity to 2.
- C . Save the Receipt, Click the Select Receipts to Void button, Select the PO Line, Change the Quantity to 5.
- D . Save the Receipt, Click the Select Items for Return button on the PO Line, Save the receipt, Receive the PO again, but change the Quantity due to 5.
A company is creating an ad hoc report indicating the number of days to complete a work order. This field is not in the database.
Which feature enables this field to be added to the report?
- A . Format
- B . Content
- C . Calculate
- D . Summaries
An administrator needs to enable a prompt in the Organizations application for users to enter the Failure Class when completing or closing work orders.
Which option is used to enable this?
- A . PM
- B . Asset
- C . Work Type
- D . Safety Plan
A quantity of 5 is received on a PO Line which has a quantity of 10. The user performed this receipt in error and wants to reverse the transaction.
Which is the most accurate statement?
- A . The Select Receipts to Void function can be used.
- B . The Select Receipts to Void function cannot be used when a partial receipt has been made.
- C . The Select Items for Return function will not allow the user to receive the PO Line at the Later time.
- D . The Select Receipts to Void function will not allow the user to receive the PO Line at a later time.