Hungry Sandwich Co. produces over 5,000 freshly made sandwiches on-site every day. The main ingredient that Hungry Sandwich Co. buys is bread. It is the item they spend the most money on, and they have a long-term partnership agreement with a local bakery to manufacture and supply fresh bread every morning. Using a supplier positioning matrix, which is the appropriate category for bread for Hungry Sandwich Co.?
Hungry Sandwich Co. produces over 5,000 freshly made sandwiches on-site every day. The main ingredient that Hungry Sandwich Co. buys is bread. It is the item they spend the most money on, and they have a long-term partnership agreement with a local bakery to manufacture and supply fresh bread every morning. Using a supplier positioning matrix, which is the appropriate category for bread for Hungry Sandwich Co.?
A . Non-critical
B . Bottleneck
C . Abundant
D . Strategic
Answer: D
Explanation:
Bread is a strategic item due to its high spend and critical role in daily operations. A partnership approach ensures consistent quality and reliability, aligning with strategic supplier management principles.
Latest L4M6 Dumps Valid Version with 120 Q&As
Latest And Valid Q&A | Instant Download | Once Fail, Full Refund