Risk is configured by default, to calculate Risk = High for a change that is scheduled with only 3 days lead time. Your customer’s change policy requires that changes be requested with 5 days lead time.
How would you satisfy this requirement?
A . Update the Risk Property for Insufficient lead time
B. Update the Risk Assessment Matrix for Insufficient lead time
C. Update the Calculate Risk UI Action
D. Update the Risk Matrix for insufficient lead time
E. Update the Risk Condition for Insufficient lead time
Answer: E