How would you minimize dependencies between the Scrum Teams?

Your management has asked you to take the lead in the development of a new product. Six teams new to Scrum will build this product.

You have gathered a number of requirements and ideas into an early form of a Product Backlog.

How would you minimize dependencies between the Scrum Teams? (choose the best answer)
A . You create an independent Product Backlog per Scrum Team.
B . You divide Product Backlog items among the six Product Owners.
C . You identify the dependencies and re-order the Product Backlog for the other five Product Owners.
D . You raise this as an impediment with the Scrum Master.
E . You work with the Developers on how to best analyze and break apart the work.

Answer: E