For this question, refer to the HipLocal case study.
HipLocal is expanding into new locations. They must capture additional data each time the application is launched in a new European country. This is causing delays in the development process due to constant schema changes and a lack of environments for conducting testing on the application changes.
How should they resolve the issue while meeting the business requirements?
A . Create new Cloud SQL instances in Europe and North America for testing and deployment. Provide developers with local MySQL instances to conduct testing on the application changes.
B . Migrate data to Bigtable. Instruct the development teams to use the Cloud SDK to emulate a local Bigtable development environment.
C . Move from Cloud SQL to MySQL hosted on Compute Engine. Replicate hosts across regions in the Americas and Europe. Provide developers with local MySQL instances to conduct testing on the application changes.
D . Migrate data to Firestore in Native mode and set up instan
Answer: B