Exam4Training

How should the Team Manager report that tolerances are forecast to be exceeded?

How should the Team Manager report that tolerances are forecast to be exceeded?
A . Create an Exception Report
B . Create a Highlight Report
C . Raise an issue
D . Grant a concession

Answer: A

Explanation:

The correct procedure for a Team Manager to report that tolerances are forecast to be exceeded is to create an Exception Report. This report is a crucial tool in PRINCE2 for escalating issues that cannot be resolved within the agreed tolerances, ensuring that they are brought to the attention of higher management for decision-making.

Reference: PRINCE2 Foundation manual, PRINCE2 official resources

Exit mobile version