How should the System Architect approach the situation?
A System Architect is working with a new ART and has planned multiple Enabler Features that explore different approaches to a technical issue that is not fully understood. The Product Manager is concerned that the ART will be wasting capacity.
How should the System Architect approach the situation?
A . Refer the Product Manager to the Enterprise Architect
B . Acknowledge the Product Manager’s concern and remove the Enablers
C . Talk directly to the developers to make sure they perform the Enabler work
D . Discuss with the Product Manager the need to assume variability and preserve options
Answer: D
Explanation:
Discuss with the Product Manager the need to assume variability and preserve options