How should the stakeholder be engaged in the project?
A member of the board of directors is the sponsor of a project that is important to the organization. This stakeholder has many other priorities and is not currently engaged in the project activities
How should the stakeholder be engaged in the project?
A . Keep the stakeholder informed and consult with them based on their needs
B . Involve the stakeholder in governance and decision making
C . Consult with the stakeholder and increase their level of interest
D . The stakeholder needs to be made aware of the project progress
Answer: A